Kitchen Remodel Contingency: How Much and What It Covers

Set a controlled reserve for hidden conditions and documented scope changes.

FIELD NOTE

Contingency is owner-controlled money for uncertainty—not a substitute for missing line items or an automatic contractor fee.

01

Separate known scope from uncertainty

Price visible, defined work in the base budget. Use contingency for conditions that cannot reasonably be confirmed before demolition, such as concealed damage, obsolete wiring, or unexpected substrate repair.

If a known appliance, permit, or finish is omitted, adding a contingency does not make the budget complete.

02

Match reserve to project risk

Cosmetic work in a recently documented home may carry less uncertainty than major layout changes in an older building. Age, previous alterations, structural changes, long-lead selections, and incomplete drawings increase risk.

03

Control how it is spent

Require written change descriptions, price, schedule impact, and approval before work proceeds except for immediate safety stabilization. Track committed and remaining contingency separately from the contract base.